D2 Subway: Dallas Central Business District (CBD) Second Light Rail Alignment
Project History and Background
D2 Study - Alternative Analysis/DEIS (2007-2015)
DART launched the D2 Study in 2007 to identify and evaluate a range of transit improvements in the Central Business District (CBD). The D2 Study focused on identifying the second phase of major transit improvements in Downtown Dallas. The improvements would ensure high quality transit service as the DART system expands to meet growing needs. In addition, it was about improving mobility and circulation to, through and within the CBD, serving local and regional mobility needs, and enhancing the ability for the DART system to grow and thrive.
The D2 Study was done in two phases. Key information from each phase is provided below:
Phase One - AA/DEIS (2010)
Phase One of the study concluded with the Alternatives Analysis/Draft Environmental Impact Statement (AA/DEIS) in May 2010. The AA/DEIS include the evaluation of four primary alternatives.Phase Two – AA/Selection of Locally Preferred Alternative (2015)
Phase Two of the study concluded in September 2015 and built on the original effort in response to comments on the AA/DEIS and because of changed conditions in downtown. These changed conditions included the new Dallas Streetcar (Oak Cliff line) and planned extensions, the Downtown Dallas 360 Plan, and proposed High Speed Rail (HSR) from Houston to downtown Dallas. These comments and issues led to new D2 Alternatives as well as refinements to those considered in the AA/DEIS.In February 2013, DART held public meetings to present the alternatives and refinements.
- View the February 13, 2013 Meeting Presentation (3.9MB PDF file opens in a new window)
Reports:
- D2 - Alternatives Refinement and Screening Report Final (3.0MB PDF file opens in a new window)
- D2 - Evaluation Results Report (53.7MB PDF file opens in a new window)
- D2 - Locally Preferred Alternative (LPA) Report Final (1.1MB PDF file opens in a new window)
- View the June 2015 D2 Study and Program of Interrelated Projects Update meeting presentation (3.5MB PDF file opens in a new window)
DART Board of Directors
September 2015 D2 Locally Preferred Alternative Map
September 2015 D2 Locally Preferred Alternative Map

Project Development for Original LPA B4 Lamar-Young/Jackson (2015-2016)
Several meetings were held during project development for the original Locally Preferred Alternative (LPA) (B4 Lamar - Young/Jackson). Meetings held during this phase, prior to the LPA Refinement Phase are summarized below:
Public Meetings
- Display Boards for June 15, 2016 Meetings (23MB PDF)
- CBD West Segment Display Board for June 15, 2016 Meetings (77MB PDF)
- CBD Central Segment Display Board for June 15, 2016 Meetings (55MB PDF)
- CBD East Segment Display Board for June 15, 2016 Meetings (96MB PDF)
- Public Meeting Presentation (Thursday, December 17, 2015, 12:00 p.m., DART Offices and 6:30 p.m., First Presbyterian Church Dallas)
- Display Boards for December 17, 2015 Meetings
Stakeholder Work Group Meetings
- Stakeholder Work Group Meeting Presentation (Wednesday, August 3, 2016, DART Offices)
- Stakeholder Work Group Meeting Presentation (Wednesday, June 1, 2016, DART Offices)
- Stakeholder Work Group Meeting Presentation (Wednesday, April 6, 2016, DART Offices)
- Stakeholder Work Group Meeting Presentation (Wednesday, March 9, 2016, DART Offices)
- Stakeholder Work Group Meeting Presentation (Wednesday, December 16, 2015, DART Offices)
Other D2 Meetings
- Interagency Coordination Meeting Presentation (Wednesday, December 16, 2015, 11:00 a.m., DART Offices)
Newsletters
- D2 Newsletter #3 (November 2016)
- D2 Newsletter #2 (June 2016)
- D2 Project Development Phase Booklet (Newsletter #1) (December 2015)
LPA REFINEMENT PHASE TO SELECT D2 SUBWAY (2016-2017)
DART conducted a Locally Preferred Alternative (LPA) Refinement phase between December 2016 and June 2017. The effort was in response to direction from the City of Dallas and the DART Board to develop D2 as a primarily-subway light rail line through Downtown Dallas. The LPA Refinement Phase culminated with the approval of the D2 Subway LPA (see LPA map), and included:
- The development of several subway alternatives with input from the general public, stakeholders, utility providers and public agencies.
- A multi-step evaluation process that consisted of a 1) elimination of fatally-flawed subway alternatives, 2) screening for reasonable set of alternatives and 3) a detailed evaluation phase for a short list of alternatives, and considered evaluation factors such as: capital costs, ridership, consistency with Board/City Council directive, affordability, constructability, transferability/connectivity with LRT lines/bus transfer facilities, underground utility considerations, access to jobs, residents and visitor/entertainment attractions, interoperability with the existing LRT Transit Mall, private property impacts, and ability to maintain train operations during construction.
Public Meetings
- Facebook Live Meeting - June 22, 2017
- Public Meeting Presentation for June 21, 2017 Meetings (19MB PDF)
- Display Boards for June 21, 2017 Meetings (54MB PDF)
- Public Meeting Presentation for April 18, 2017 Meetings (20MB PDF)
- Public Meeting Presentation for January 19, 2017 Meetings (7MB PDF)
Deep Ellum Charrette
- Resource Materials for Charrette (41MB PDF)
Stakeholder Work Group Meetings
- Joint Stakeholder/Technical Committee Meeting Presentation (Wednesday, May 17, 2017, DART Offices)
- Joint Stakeholder/Technical Committee Meeting Presentation (Wednesday, March 22, 2017, DART Offices)
- Stakeholder Work Group Meeting Presentation (Wednesday, January 18, 2017, University of North Texas System Building, Downtown Dallas)
- Stakeholder Work Group Meeting Presentation (Wednesday, December 7, 2016, Sheraton Dallas Hotel)
(Note: To view a video demonstrating a Tunnel Boring Machine, click on the image on page 16.)
Technical Committee Meetings
- Joint Stakeholder/Technical Committee Meeting Presentation (Wednesday, May 17, 2017, DART Offices)
- Joint Stakeholder/Technical Committee Meeting Presentation (Wednesday, March 22, 2017, DART Offices)
- Technical Committee Meeting Presentation (Thursday, February 23, 2017, DART Offices)
- Technical Committee Meeting Presentation (Thursday, February 9, 2017, DART Offices)
- Technical Committee Meeting Presentation (Thursday, January 12, 2017, DART Offices)
- Technical Committee Meeting Presentation (Thursday, December 15, 2016, DART Offices)
- D2 Subway Reasonable Alternatives Assessment and Screening Evaluation Results Report (24.3MB PDF file opens in a new window)
- D2 Subway Detailed Definition and Evaluation Results Report Final (24.4MB PDF file opens in a new window)
- D2 Subway Locally Preferred Alternative (LPA) Report Final with Appendices (14.1MB PDF file opens in a new window)
- On September 6, 2017 DART provided its annual Capital Investment Grant (CIG) program submittal to the Federal Transit Administration in support of a future Core Capacity federal funding grant request for approximately 50% of the project cost.
- On September 12, 2017 the DART Board of Directors approved a debt resolution for the D2 Subway. This debt resolution provides flexibility to DART to issue debt to finance the project should DART not receive the anticipated Federal grant. Additionally, they approved the FY18 20-Year Financial Plan and FY18 Budget, both of which include the D2 Subway project.
- On September 13, 2017 the Dallas City Council approved the Victory/Commerce/Swiss D2 Subway alignment as the Locally Preferred Alternative.
- On September 26, 2017 the DART Board of Directors selected and approved the Commerce via Victory/Swiss Alternative as the Locally Preferred Alternative.